Location Prnjavor, 7 independent power plants, total power 1,720KW.
The project started in September 2023 and ended in December 2023. The power plant was connected to the electrical energy system of the RS in January 2024, with successfully completed technical acceptance and use permit.
Total energy produced as of August 2024 over 1,800 MGW
We are currently in the construction phase of the second part of the project with a total power of 1.2 MGW, which we expect to be completed in November 2024.
Airpoint 1
Two independent power plants with a power of 250 KW each
The project started in March 2024 and ended in June 2024. The power plant connected to the power distribution system in August produced over 120 MGW in the first 30 days
Planned construction of Airpoint 2 in 2025
Jupiter 1
Location Donja Bistrica Banja Luka, 3 independent power plants of 150 kW with a total power of 450 kW
The project will start in September 2024 and the planned completion of the works in November 2024.